National Wildlife Federation Comments on Devils Lake outlet
Corps of Engineers Draft Environmental Impact Statement
Page 3
-bracket the potential effects for the two moderate lake
scenarios [emphasis added] selected for analysis
The outlet plan preliminarily selected for design does not
originate in West Bay and falls somewhat outside the bounds for
this analysis [emphasis added]. The water quality effects on
aquatic resources would likely be [emphasis added] very similar
to those identified with the West Bay 300 cfs outlet, constrained
by water quality and channel capacity. However, since a Pelican
Lake outlet captures the fresh water flowing into Devils Lake,
the outlet would have substantially higher flows, and the effects
of increased flow on aquatic habitat in the Sheyenne River would
likely be [emphasis added] closer to the effects identified with
the West Bay 480 cfs outlet. In lieu of additional modeling, the
water quality effects of the 300 cfs constrained operation and
the flow effects of the 480 cfs unconstrained operation were used
to evaluate the potential effects of the Pelican Lake outlet on
aquatic resources. (DEIS p. 5-45)
In discussing the impacts of the operation of the proposed
Pelican Lake 300 cfs outlet on the Sheyenne River under the more
moderate 1450 feet lake future scenario, the DEIS
shows a typical operation year that imposes 300 cfs
flows from the outlet on Sheyenne River base flows that peak at
200 cfs in July and average less than 100 cfs from May 1 through
September 1, with flows from the outlet dropping to an average of
perhaps 50 cfs from September 1 through November 30 (DEIS Figure
35, p. 5-50). Therefore, in a typical operation year
under the 1450 moderate scenario, it appears that the
Pelican Lake 300 cfs outlet would be expected to discharge about
80,000 acre-feet of water from Devils Lake to the Sheyenne River.
Under these moderate conditions, the DEIS states
that:
Operation of the Pelican Lake outlet would result in a
substantial change in the flow regime of the Sheyenne River.
Discharges of up to 300 cfs over a major portion of the summer
would represent a 5- to 10-fold increase in summer/fall flows
along the Sheyenne River. (DEIS p. 5-48)
the outlet could result in up and down flows with
sudden and extreme fluctuations in flow. These are the types of
situations that made it difficult for species to adapt to habitat
conditions. (DEIS p. 5-48)
The changes in flow duration, stage and frequency could
result in an increase in erosion and sedimentation on Sheyenne
River. (DEIS p. 5-52)
The changes on the Sheyenne River in water quality,
hydrology, geomorphology and habitat could result in substantial
changes in aquatic biota. (DEIS p. 5-53)
Even under a constrained operation approach, the levels of
many water quality constituents are increased by two to three
times to concentrations just below the established water quality
standards. (DEIS p. 5-53)
although water quality standards on the Sheyenne
River are not violated, the percent of time any particular
concentration is exceeded increases dramatically. For example,
sulfate exceedences go from zero to 42 percent for the 250 mg/l
sulfate level. (DEIS p. 5-53)
The loss of habitat due to increased flows, changes in
channel geometry, loss of overbank cover and sedimentation,
coupled with changes in water quality and algal growth, would all
contribute to a substantial change in the aquatic community
present in the Sheyenne River. Projected water quality changes
associated with outlet operation may adversely influence fish
reproduction and result in lost-year classes. The cumulative
result of all these changes would be a decrease in diversity and
density of aquatic species in the Sheyenne River. The threshold
chloride levels of some aquatic species, such as mussels, would
be approached with operation of an outlet; however, no effects
are anticipated. (DEIS p. 5-53)
Many of the effects associated with the operation of an
outlet cannot readily be quantified. (DEIS p. 5-96)
Some of the aquatic losses would not be mitigated; for
example, loss of invertebrates, loss of fish year classes, loss
of wetted usable area due to increased channel width, and changed
channel morphology. (DEIS 5-97)
Changes in the aquatic community would persist for many
years after outlet operation ceased, especially on the Sheyenne
River above Lake Ashtabula. (DEIS Appendix D, p. D-31)
the 300 cfs [West Bay] constrained pumping
alternative would cause much less damage than the 480 cfs [West
Bay] unconstrained pumping alternative [which approximates the
flow impacts of a 300 cfs Pelican Lake outlet] under either the
moderate or wet climatic scenario. (DEIS Appendix A, p.
A-254)
The flow impacts due to a Pelican Lake alternative could be
dramatic, particularly in the upper Sheyenne, which is
essentially isolated from recolonization. Water quality changes
would be devastating to unionids. (DEIS p. 5-102)
Substantial to significant adverse impacts on aquatic
habitat availability and suitability can be expected under most
if not all of the Devils Lake outlet options. The most flow
sensitive habitat types, such as riffles where shallow, fast
habitats predominate, would be almost entirely eliminated for a
majority of the year. The largest adverse impacts on habitat
would likely occur in the Sheyenne River above Lake Ashtabula,
where stages are projected to increase up to 3 feet. (DEIS
Appendix C, p. C-38)
Downstream interests would bear most of the negative
impacts of this [480 cfs] plan [which reflect the water quantity
impacts of a Pelican Lake 300 cfs outlet]. Flooding may increase,
primarily on agricultural lands along the Sheyenne River. Higher
flows may exacerbate streambank erosion that may threaten
farmstead structures and residences along the river. The added
flow translates into stage increases, resulting in additional
damage to structural property from direct flooding. Under these
circumstances, flood easements would be purchased to compensate
landowners for future expected losses to their properties. The
potential for bearing these adverse impacts of an outlet is a
source of controversy with downstream interests and has produced
conflict with their upstream neighbors. (DEIS p. 4-10)
As in the case of an overflow, farms that withdraw water
from the Sheyenne River or the Red River for irrigation could
suffer reduced crop yields from the lower river water quality
associated with an outlet. Exacerbated flooding in the Sheyenne
River could damage agricultural property, including lands,
equipment, and structures. Also, higher flows in the river could
affect some farms that straddle the river
These river
crossings may be impeded or prohibited by additional river flow
associated with an outlet. (DEIS p. 5-42)
In rare instances, there could be overbank flooding due to
unforecasted rainstorms and the inability to turn the outlet off
in time. (DEIS p. 5-56)
Using a _ mile area of influence, groundwater changes could
potentially affect about 112,000 acres of riparian lands along
the Sheyenne River and 76,000 acres along the Red River.
(DEIS p. 5-57)
Although the Sheyenne River channel appears currently
stable, channel instability may be onset if the flows are
increase[d] due to the operation of an outlet
The process
of channel adjustment may take 50 to 100 years or more.
(DEIS Appendix C, p. C-69)
There is an increased risk of transfer of biota or the
increase in the distribution of existing organisms associated
with any feature that improves the connectivity between systems
that have been segregated for many centuries. (DEIS 5-56)
As noted above, the DEIS shows that, in a typical operation
year under the more moderate 1450 feet future
lake level scenario, the proposed Pelican Lake 300 cfs outlet
would discharge approximately 80,000 acre-feet of water from
Devils Lake to the Sheyenne River, primarily from May through
August. Although the DEIS does not show a typical operation
year for the Pelican Lake 300 cfs outlet under the wet
future scenario, in order to prevent an overflow, it
appears that the outlet would have to operate at its 300 cfs
maximum capacity for the full seven months from May 1 to November
30 every year. For example, with the lake reaching 1457 feet even
with the outlet in operation (DEIS p. 5-86), it would have a
surface area of approximately 230,000 acres (DEIS Figure 7, p.
2-26). The average annual 21 inches of precipitation in the
Devils Lake area during the 1993-1999 period on which the wet
future scenario is based (DEIS p. 4-12) would contribute
402,500 acre-feet of precipitation directly to the surface of the
lake each year. With the additional average 317,000 acre-feet of
inflows during that period (DEIS p. 1-5), total annual accruals
would average 719,000 acre-feet through the first 21 years of the
wet future scenario. The average annual 29 inches of
evaporation through the 1993-1999 period (WEST Consultants, Inc.,
2001) would be expected to remove 556,000 acre-feet per year from
the lake, leaving an average annual net accrual of 162,000
acre-feet that would have to be removed by the outlet to prevent
the lake from continuing to rise above 1457 feet. A 300 cfs
outlet operating at maximum capacity for seven months would
remove 126,000 acre-feet per year, so it appears that the Pelican
Lake 300 cfs outlet would have to operate at maximum capacity
from the fifth through the 21st year (DEIS Appendix A, p. A-110)
of the a wet future scenario in order to prevent the
lake from overflowing to the Sheyenne River and justify its
construction.
Because the downstream impacts of the operation of the proposed
Pelican Lake 300 cfs outlet have not been modeled, the DEIS
attempts to interpret the possible impactsexamples of which
are cited abovebased on the water quality impacts of a 300
cfs constrained West Bay outlet and the water quantity impacts of
a 480 cfs unconstrained West Bay outlet modeled under moderate
future lake conditions of 1450 and 1455 feet. However:
A wet future in the Devils Lake basin would also probably
result in a wet future in other basins. (DEIS p. 5-81)
including the Sheyenne River Basin, and the statements that:
The primary downstream area affected would be those areas
flooded when the flow on the upper and lower Sheyenne River reach
1,000 and 1,500 cfs, respectively. (DEIS Appendix C, p.
C-138)
and:
Operation of an outlet at 300 cfs would have limited effect
on the extent or duration of flooded area along the upper or
lower Sheyenne River with flows not exceeding 1,000 or 1,500 cfs,
respectively. (DEIS Appendix C, p. C-138)
indicate that the operation of the outlet would not, in fact, be
constrained to the 600 cfs capacity of the Sheyenne River channel
during a wet future scenario as claimed (DEIS p.
3-14, 4-18), so the impacts could be expected to be substantially
greater and more severe than those described under the moderate
future scenarios discussed in the DEIS.
It is instructive, therefore, to consider how the DEIS describes
the downstream impacts associated with the more than 50 percent
increase in discharges from these moderate conditions
(from 80,000 acre feet to 126,000 acre-feet per year) of a
Pelican Lake 300 cfs outlet operating under wet future
scenario conditions where the Sheyenne River would already
be experiencing unusually high flows:
Because the scenario is based on a wet climate, the pumping
may [emphasis added] last longer and greater quantities may
[emphasis added] may be pumped out. Therefore, the impacts
described for the stochastic analysis would last longer and the
flow effects would be greater. For example, erosion would be
more, aquatic effects from flow would be the same type but would
be of a greater magnitude, soil salinity effects would also be of
the same type but irrigators and land users would be subject to
those effects for a longer period. (DEIS 5-86)
In summary, changes in hydrology would be significant with
a Pelican Lake alternative because large amounts of water could
be discharged during wet periods in the Devils Lake Basin due to
improved water quality. Erosion will be greater, summer nursery
habitat will be less, unproductive habitat will increase in
summer and fall, and change in flow magnitude between fall and
winter will be greater. Therefore, aquatic communities may
survive the water quality changes of the alternative, only to be
affected by the change in habitat and hydrology. The changes in
the aquatic community would persist for many years after outlet
operation has ceased. (DEIS p. 5-55)
Thats it! These two paragraphs are the sum and substance of
what the public, the Congress and other decision-makers are told
about the specific environmental impacts of the operation of the
proposed Pelican Lake 300 cfs outlet in the wet future
scenario under which outlet proponents such as the North
Dakota congressional delegation, Ramsey County elected officials
and Lake Emergency Management Committee representatives are
advocating that the outlet be justified (Associated Press,
2002a).
Of course, the reader is told that more detailed discussion of
the impacts under the scenario future is presented in the
Technical Appendices (DEIS p. 5-66), but examination of Appendix
C, which addresses Environmental Resources, reveals
only the same kinds of abstract and ambiguous generalizations
that are used in the DEIS itself to minimize and obfuscate the
downstream impacts of the operation of the proposed Pelican Lake
300 cfs outlet under the wet future scenario
necessary to rationalize its construction.
The failure of the DEIS to provide the detailed statement of the
qualitative and quantitative environmental impacts of the
construction and operation of the proposed Pelican Lake 300 cfs
outlet required by NEPA renders the DEIS technically inadequate
and legally deficient on its face.
Devils Lake Outlets Technically Unsound and Economically
Unjustified
The DEIS concludes that the proposed Pelican Lake 300 cfs outlet
only:
Minimally reduces flood damages around the lake and
moderately reduces the potential for a natural overflow event.
(DEIS p. 4-38)
However:
When balancing the project needs and objectives, including
cost effectiveness, downstream water quality impacts, and other
considerations, the Pelican Lake 300 cfs outlet alternative is
the best overall outlet plan. Additionally, it is moderately
effective in controlling future lake levels (DEIS 1-S-7).
Under a conventional stochastic analysis, the proposed Pelican
Lake 300 cfs outlet would reduce the expected lake stage from
1450 feet without the outlet to 1449.5 feet with the outleta
half foot reduction (DEIS p. 1-S-4). Without the outlet, there is
a 50.6 percent chance that the lake would reach or exceed 1450
feet and a 20.8 percent chance the lake would reach or exceed
1454 feet (DEIS p. 1-S-4-5). The outlet would reduce the chance
that Devils Lake would reach elevation 1459 feet where it would
begin to overflow to the Sheyenne River from 9.4 percent to 4.1
percent (DEIS p. 5-71). Devils Lake would have to rise to
1460.6 before there would be a significant flow (at least 300
cfs) to the Sheyenne River (DEIS p. 2-9), and the proposed
Pelican Lake 300 cfs outlet would reduce the chance of that
occurring by 2 percent, from 4 percent without the outlet to 2
percent with the outlet (DEIS Appendix B, Table II.ST-2, p.
B-195). However, the 1 percent chance that Devils Lake would
reach elevation 1463 feet where the damages would be the greatest
(DEIS p. 2-9, 5-71-84; Appendix C, p. C-124) still remains at 1
percent even if the Pelican Lake 300 cfs outlet is built (DEIS
Appendix B, Table II.ST-2, p. B-195). Thus, the outlet would do
virtually nothing to prevent the most serious damages resulting
from an overflow of Devils Lake at 1463 feet.
Under the wet future scenario, the lake would
continue to rise another 10 feet from the January 2002 elevation
of 1447.1 feet to 1457 feet even with the outlet in operation
(DEIS p. 5-89), and with any significant increase in
precipitation from the 1993 to 1999 average, it also would
overflow to the Sheyenne River (see The Wet Future Scenario
Fantasizing Feasibility below). Moreover, as pointed out
above, during a wet future scenario when the Sheyenne
River already has high flows, the operation of the outlet would
have to be constrained below its maximum capacity, in which case
it would be even less effective in preventing the lake from
continuing to rise above 1457 feet, or, if operated at maximum
capacity, it would result in even more severe downstream impacts
on the Sheyenne River. Consequently, the proposed Pelican Lake
300 cfs outlet is technically unsound on its face.
According to the DEIS:
Therefore, there is about a 75 percent chance that if an
outlet were built it would not be economically beneficial.
(DEIS p. 1-S-5)
The outlet plan that has been preliminarily selected for
design is not economically justified using methods that would
determine expected net benefits by producing probability-weighted
benefits and costs. (DEIS p. 1-S-7)
The outlet alternative under the stochastic analysis with
the highest benefit-cost ratio (although it is not shown to be
economically justified) is the Pelican lake 300 cfs outlet.
(DEIS p. 4-3)
The benefit-cost ratio for the proposed Pelican Lake 300 cfs
outlet under the stochastic analysis is 0.37 (DEIS Table 4, p.
4-2). This is even less than the 0.69 benefit-cost ratio of
taking no additional action whatsoever in the Devils Lake Basin
to protect the local infrastructure (DEIS p. 3-24, Table 4, p.
4-2). The benefit-cost ratios for the other outlet alternatives
considered are: West Bay 300 cfs outlet = 0.28, West Bay 480 cfs
outlet = 0.01, Pelican Lake 480 cfs outlet = 0.10, Pelican Lake
Bypass 480 cfs-PL 2 = 0.14, Pelican Lake Bypass 480 cfs-PL3 =
0.21, and East End Outlet = 0.02 (DEIS Table 4, p. 4-2)
The Energy and Water Development Appropriations Acts for Fiscal
Years 1998, 1999, 2000 and 2001 specify:
That the economic justification for the emergency outlet
shall be prepared in accordance with the principles and
guidelines for economic evaluation as required by regulations and
procedures for the Army Corps of Engineers for all flood control
projects, and that the economic justification be fully described,
including the analysis of the benefits and costs, in the project
plan documents. (DEIS p. 1-2)
The DEIS states that:
The Corps of Engineers traditionally recommends plans that
show the greatest expected net benefits, where benefits exceed
costs based on the probability of events. As a standard process
under the Principles and Guidelines, this is referred to as the
National Economic Development, or NED, plan. A stochastic
approach was used for economic evaluation. The benefit-cost ratio
of the best outlet plan incorporating probabilities of occurrence
is 0.37. (DEIS Abstract)
The proposed Pelican Lake 300 cfs outlet, therefore, is without
economic justification under the law, as well as under the Corps
own Principles and Guidelines. Consequently, the Corps has no
alternative under the law except to recommend that the outlet not
be built.
Hidden Costs
The DEIS lists the Total First Cost of the proposed Pelican Lake
300 cfs outlet as $97,651,000 (DEIS Table 3, p. 3-23) and the
Total Costs at $117,000,000 (DEIS Table 4, p. 4-2) to
$125,000,000 (DEIS Table 6, p. 4-13). However, because the lake
would continue to rise under the wet future scenario
even with the outlet (DEIS. p. 5-86), it still would be necessary
to incur the additional costs of implementing infrastructure
protection measures (DEIS p. 5-89), including raising the levees
protecting the City of Devils Lake, relocating homes, building
temporary levees, raising selected roads and railroads, and
protecting or relocating utilities (DEIS p. 3-9).
The DEIS estimates these additional infrastructure protection
costs under the wet future scenario without the
outlet and the lake reaching 1460.6 feet (DEIS Table B, p. 1-S-4)
at $585 million (DEIS Table 6, p. 4-13). With the outlet in
operation and the lake reaching 1457 feet, (DEIS p. 5-86)just
two feet below overflow elevation, it might be assumed that these
infrastructure protection costs still could reach $300 to $400
million. Therefore, the total cost of implementing the Pelican
Lake 300 cfs outlet plus the associated infrastructure protection
for a lake level of 1457 feet required with this alternative is
not the $125 million shown in the DEIS, but likely is in the
range of $425 to $525 million.
The Wet Future Scenario Fantasizing Feasibility
In outlining the rationale for evaluating alternatives under a
wet future scenario, the DEIS explains that:
The stochastic modeling was based on an assumption of the
stationarity of the climate. Because of the uncertainty of and
the differing scientific opinions regarding future climatic
conditions in the Devils Lake basin, a scenario based analysis
was also performed. In situations of uncertainty, the Principles
and Guidelines allow for development of alternative future
conditions, or scenarios. This scenario based analysis was used
to specifically address potential solutions to the problems in
the basin if the recent wet conditions continue. (DEIS
Abstract)
The scenarios for Devils Lake include the WET future, the
moderate trace 1445, an even more moderate trace 1450, and a DRY
future. The WET future assumes that the years 1993 to 1999 would
occur for two cycles. At this point the lake would reach the
overflow elevation of 1459 in the year 2014. The period 1993 to
1999 is repeated again to generate overflow and then the years
1980 to 1990 to finish out 50-yrs. The WET future was necessary
to assess the impacts of a natural overflow from Stump Lake to
the Sheyenne River. (DEIS Appendix A, p. A-21).
The wet future scenario analysis evaluated one set of
50-year lake levels that is based on very recent climatic
conditions for the years 1993-1999. The wet future scenario
repeats the climatic and hydrologic conditions for the seven
highest inflow years in recent history (1993-1999) for three
cycles, causing the lake to overflow. The remaining years of the
50-year cycle were defined assuming climatic and hydrologic
conditions similar to 1980 through 1999, and then 1980 through
1990, to complete the 50-trace. (DEIS p. 3-5)
The DEIS offers no evidence and makes no claim that the wet
future scenario provides a more reliableor even
remotely more realisticanalysis of future lake conditions
than the stochastic analysis. On the contrary, the DEIS points
out that:
The duration of the recent wet conditions cannot be
determined definitely because of the complex interactions between
global weather factors. (DEIS Appendix A, p. 1-18)
As indicated by the regional Weather Information Center,
climatic conditions during 2000-15 are expected to be similar to
conditions during 1980-99. (DEIS Appendix A, p. 1-18)
No one can know or predict with confidence climate 50 years
into the future. The National Academy of Sciences (NAS) provided
guidance for another study (citation omitted) on analysis when
the future is uncertain. They warn that, Failure to deal
explicitly with uncertainty leads the unwary to have far too much
confidence in the resulting forecast and analysis, which can lead
to bad public decisions [emphasis added]
(DEIS
Appendix A, A-20)
While the use of a wet future scenario may provide insight
into potential benefits of the outlet alternatives, such an
analysis provides little assurance as to the soundness of such an
investment, since it is tied to the unlikely assumption that a
particular scenario will ever occur. (DEIS p. 4-40)
The probability of the scenario future occurring is
practically zero because it is an artificial scenario.
(DEIS p. 5-88)
The alternatives were evaluated using an alternate future
without conditions, which assumes a continued wet climate
scenario based on the climate sequence from 1993 through 1999
repeated until a natural overflow to the Sheyenne River occurred.
The probability that the lake will rise exactly in this way is
zero. (DEIS p. 5-71)
Thus, the wet future scenario has nothing to do with
reality, but is simply a set of manufactured conditions
specifically created to result in just enough precipitation over
a 21-year period to cause the lake to overflow without the
Pelican Lake 300 cfs outlet, but not so much that the lake would
still overflow even with the outlet. But, of course, The
probability that the lake will rise exactly in this way is zero
(DEIS p. 5-71). Nevertheless, proponents of the outlet cite this
artificially contrived scenario as justification for building the
outlet. For example:
The key to getting a Devils Lake outlet, one official says,
is to persuade the Army Corps of Engineers [to] accept a
so-called wet-cycle scenario.
Ramsey County Commissioner Joe Belford said that if the corps
accepts the premise that the wet cycle of the last eight years
will continue for another 10 years or more, the project easily
would meet federal benefit-cost requirements. (Associated
Press, 2002b)
Of course, the Corps cannot accept a premise that the wet cycle
of the last eight years (2001 was not a wet year in the Devils
Lake Basin) will continue for another 10 years because it is
without valid scientific foundation. However, rather than dealing
with the matter on a rational, factual basis:
Mike Connor, manager of the Devils Lake Basin Joint Water
Board said
I think its time for people to
hollar a little bit
Well, maybe not a little bit, maybe a
whole lot. (Associated Press, 2002b)
Unfortunately, this has been the approach universally employed by
proponents of an outlet from Devils Lake since the lake began its
rapid rise in 1993. The Corps, however, is obligated to take a
more responsible approach, and it is required under NEPA to
recognize and respond substantively to the National Academy of
Sciences admonition that failure to deal explicitly with
uncertainty leads the unwary to have far too much confidence in
the resulting forecast and analysis, which can lead to bad public
decisions. The proposed outlet from Devils Lake reflects
precisely such a failure to deal explicitly with uncertainty
leading the North Dakota congressional delegation, the Governor,
the State Water Commission and other unwary proponents of the
outlet to have far too much confidence in the wet future
scenario and, therefore, to advocate a bad public decision.
According to the DEIS:
To better understand the sensitivity of assumptions used
for future lake conditions, both with and without project, the
alternatives were evaluated in comparison to other possible
conditions. (DEIS p. 3-24).
Those conditions were (1) No Action Protection Strategy, (2)
Moderate Future Scenarios, (4) Erosion of Natural Outlet, and (5)
Proposed Temporary Outlet As Part of Future Conditions (DEIS pp.
3-24-25). However, the DEIS does not provide a sensitivity
analysis of the proposed Pelican Lake 300 cfs outlet itself under
a wet future scenario. As noted above, the wet
future scenario is a manufactured set of conditions
specifically contrived to result in just enough precipitation
over the next 21 years to cause the lake to overflow without the
outlet, but not so much that it would still overflow even with
the outlet. Therefore, it would be helpful to the public and to
decision-makes in understanding the tenuous nature and dubious
relevance of the wet future scenario for the Corps to
perform a sensitivity analysis of the outlet itself to show the
effect on the efficacy and benefits of the proposed outlet of
variations from the specific wet future scenario
conditions outlined in the DEIS. For example, at elevation 1457
feet, the expected lake stage with the proposed
Pelican Lake 300 cfs outlet after the first 14 years of the
wet future scenario (DEIS Table B, p. 1-S-4; Appendix
A p. A-21), the lake would have a surface area of approximately
230,000 acres (interpolated from DEIS Figure 7, p. 2-6). Annual
inflows to the lake from 1993 to 1999 averaged 317,000 acre-feet
(DEIS p. 1-5) and precipitation, which averaged 21.0 inches from
1993 to 1999 (WEST Consultants, Inc., 2001) would contribute
another 402,500 acre-feet to the 230,000 acre lake, for average
total annual accruals of 719,000 acre-feet. Evaporation, which
averaged 29.0 inches, or 2.42 feet, during the period (WEST
Consultants, Inc, 2001), would remove 319,440 acre-feet, and the
outlet, operating at maximum capacity for seven months would
remove another 126,000 acre-feet, leaving a net gain of 36,900
acre-feet per year under the wet future scenario.
If average annual precipitation in the Devils Lake Basin under
the wet future scenario were to increase by one inch
(5 percent) above the 1993-1999 level, average annual inflows
might be expected to increase from 317,000 acre-feet to 332,850
acre-feet and direct precipitation on the lake would increase
from 402,500 acre-feet to 420,900 acre-feet, for an increase in
total average annual accruals to 753,750 acre-feet. Evaporation
would remove a little more than 319,440 acre-feet because the
surface area of the lake would be a little larger, but the outlet
still would remove only 126,000 acre-feet, leaving a net gain of
about 71,000 acre-feet, or about 3.7 inches, per year, bringing
the lake dangerously close to the overflow elevation of 1459 feet
by the end of the third seven years of the wet future
scenario. An increase in average annual precipitation under
the wet future scenario of two inches (10
Next Page 4
Back to Page 2