Web Page 1 2
3 4 5 6 7
COMMENTS OF
THE NATIONAL WILDLIFE FEDERATION
ON
THE U. S. ARMY CORPS OF ENGINEERS
FEBRUARY 2002
DRAFT DEVILS LAKE, NORTH DAKOTA,
INTEGRATED PLANNING REPORT AND
ENVIRONMENTAL IMPACT STATEMENT
Prepared by
Gary L. Pearson
1305 Business Loop East
Jamestown, North Dakota 58401
and
David R. Conrad
National Wildlife Federation
1400 Sixteenth Street, N. W.
Washington, D. C. 20036-2266
May 6, 2002
TABLE OF CONTENTS (Page references are for the written document,
not these web pages)
Page
Introduction 3
Flawed Scoping Process 4
Inappropriate Tiering of Environmental Impact Analysis 5
Failure to Consider Cumulative Impacts 7
Red River Valley Water Supply Project 7
Inlet to Deliver Missouri River Water to Devils Lake 8
North Dakotas 300 cfs Temporary Emergency
Outlet 9
Absence of Authorization to Construct and Operate an Outlet 11
Inadequate Description of Environmental Impacts of the Proposed
Action 12
Devils Lake Outlets Technically Unsound and Economically
Unjustified 16
Hidden Costs 18
The Wet Future Scenario Fantasizing Feasibility 18
The $125 Million Lottery Ticket 21
Erosion of the Natural Outlet Indulging Geologic Fiction
21
Wetlands, Wetland Drainage and Wetland Restoration 25
Water Resource Management in the Devils Lake Basin 26
Wetlands and Wetland Drainage in the Devils Lake Basin 29
Contribution of Wetland Drainage to the Rise of Devils Lake 30
Wetland Restoration and Upper Basin Storage 32
Continuing Wetland Drainage in the Devils Lake Basin 36
Inflated Values and Exaggerated Benefits 38
Flooding at Devils Lake Hardships, Handouts and False
Hopes 39 Biota Transfer Confusing Absence of Proof with
Proof of Absence 43
Mythical Mitigation 47
U. S. Army Corps of Engineers Environmental Operating Principles
53
Conclusions 53
Introduction
Devils Lake in northeastern North Dakota is located in a 3,814
square-mile closed sub-basin of the Red River of the North Basin,
which is part of the Hudson Bay Drainage Basin. The Sheyenne
River passes eastward near the southern boundary of the basin
before looping 400 miles south, east and then north again to join
the Red River of the North at Fargo, North Dakota. The Red River
of the North then flows north into Canada where it empties into
Lake Winnipeg at Winnipeg, Manitoba.
The geologic record shows that, since Devils Lake was formed
10,000 years ago by the Wisconsin Glacier, its level has
fluctuated widely over a range of some 65 feet, from dry at 1394
feet above mean sea level (msl) to overflowing to the Sheyenne
River at 1459 feet. At elevation 1446.6 feet, Devils Lake
overflows to the east through the Jerusalem Spillway to West
Stump Lake and East Stump Lake before the combined lakes then
rise to overflow from West Stump Lake to the Sheyenne River
through the Tolna Coulee. At its overflow elevation of 1459 feet,
Devils Lake has a surface area of approximately 300,000 acres.
The lake last was at its current elevation of 1447 feet at the
time white settlers arrived in the area in the early 1800s. The
lake supported a thriving commercial and sport northern pike
fishery and a small side-wheel steamer, the Minnie H, operated
between the town of Devils Lake and Church's Ferry at the
northwestern end of the lake. The ferry docked near a large rock
that remains near current downtown Devils Lake. The lake had
declined to elevation 1438 feet by the time its level first was
officially recorded in 1867, and by 1889 the northern pike
fishery disappeared when the lake dropped to 1424 feet. The lake
continued to decline to its modern day low of 1401 feet in 1940,
after which it began an erratic rise to elevation 1423 feet by
1992. However, by 1975 Devils Lake had risen to 1425 feet, and
developments which had been encroaching on the bed of the lake as
it had receded already were being threatened by the rising water.
By 1983, the State was petitioning the U. S. Army Corps (Corps)
to construct an outlet from Devils Lake to the Sheyenne River.
The severe drought of 1988 to 1992 was followed by seven years of
unusually high levels of precipitation that resulted in the lake
rising from 1423 feet in 1992 to 1448 feet in 2001. The lake
currently is at 1447 feet and is expected to drop another two
feet this year. However, the dramatic rise of the lake starting
in 1993 generated renewed pressure for the construction of an
outlet to the Sheyenne River, and in 1996 the Corps released an
Emergency Outlet Plan, Devils Lake, North Dakota that
examined two outlet routes from West Bay of Devils Lake to the
Sheyenne River (U. S. Army Corps of Engineers, 1996), and the
Emergency Supplemental Appropriations Act of 1997 (P. L. 105-18)
appropriated $5,000,000 and directed the Corps to use the funds
to:
initiate and complete preconstruction engineering and
design and the associated Environmental Impact Statement for an
emergency outlet from Devils Lake, North Dakota, to the Sheyenne
River. (U. S. Army Corps of Engineers and North Dakota
State Water Commission, 2001)
The Corps received an additional $6 million for preconstruction
engineering and design of the outlet and the associated
environmental impact statement in Fiscal Year 2000 ($2 million)
and 2001 ($4 million) supplemental appropriations (U. S. Army
Corps of Engineers and North Dakota State Water Commission,
2001).
A notice of availability of the February 2002 Draft Devils Lake,
North Dakota, Integrated Planning Report and Environmental Impact
Statement (DEIS) was published in the March 8, 2002, Federal
Register. The following comments are submitted in response to
that announcement for inclusion in the official record of public
comments on the Draft Devils Lake, North Dakota, Integrated
Planning Report and Environmental Impact Statement.
Flawed Scoping Process
In their March 1998 joint Devils Lake Emergency Outlet
Newsletter, Issue #1, the Corps and the North Dakota State
Water Commission (NDSWC) announced a series of Public
Scoping Meetings where members of the public would have
opportunities to (1) learn about scoping issues which already had
been identified by local, State and Federal regulatory agencies
and public officials, (2) identify issues which they felt were
important, (3) help to prioritize the scoping issues that had
been identified, and (4) submit comments on the proposed outlet
from Devils Lake to the Sheyenne River (U. S. Army Corps of
Engineers and North Dakota State Water Commission, 1998).
However, by already having obtained lists of scoping issues from
local, State and Federal officials before the public scoping
process was announced and conducted, and by already having
proposed a variety of outlet alternatives in six reports dating
back over a period of 18 years before the scoping process was
initiated, the Corps violated the guidelines for scoping of
environmental documents prepared pursuant to the National
Environmental Policy Act (NEPA) (Pearson, 1998). In addition, the
scoping process utilized by the Corps in 1998 was designed to
discourage and frustrate, rather than encourage and facilitate,
public participation and involvement (Pearson, 1998).
In an attempt to bestow economic feasibility on the proposed
outlet from Devils Lake and under pressure from the North Dakota
congressional delegation, the purpose of an outlet was expanded
in 2001 from reducing the damages from flooding at Devils Lake to
include reducing the already low potential for a natural overflow
to the Sheyenne River (U. S. Army Corps of Engineers and North
Dakota State Water Commission, 2001).1 Therefore, the Corps and
the NDWSC announced in their March 2001 Devils Lake Study
Newsletter that new directions had been set for
the study and that a series of supplemental public scoping
meetings would be held to (1) update the public on the
current status of the study, (2) seek comments regarding the
alternatives that the Corps would be carrying into the next phase
of the study, and (3) identify any new issues associated
with those alternatives. However, because, the public was
deprived of meaningful opportunities for input on the issues and
alternatives that had been identified by local, State and Federal
government officials and presented in the initial 1998 scoping
meetings, the restriction in these supplemental scoping meetings
three years later to comments on new issues regarding
alternatives that the Corps would be carrying forward (U.
S. Army Corps of Engineers and North Dakota State Water
Commission, 2001) simply perpetuated the systematic denial of
meaningful participation by the public in the scoping process.
As one example of failure of the Corps scoping process to
incorporate public comments in a meaningful and substantive way,
numerous comments were submitted by the public raising the issue
of the contribution of wetland drainage in the Devils Lake Basin
to the recent rise in the lake (See, e.g., Pearson, 2001), and
the Corps even acknowledges in its Environmental Justice Analysis
that:
Findings from this study revealed a noticeable lack of
definitive information available from agency sources on a number
of issues, such as
impacts to Devils Lake flooding of upper
basin drainage. (DEIS Appendix C, p. C-102)
However, the DEIS does not include upper basin drainage among the
areas of controversy or unresolved issues identified during the
EIS process (DEIS p. 1-S-9-13). Similarly, although it includes
such things as rocketing and weather patterns among
issues to be summarized or not addressed, the DEIS makes no
mention at all of upper basin drainage as being among the
issues identified during the scoping process (DEIS
Appendix C, pp. C-133-136).
This failure of the Corps public scoping process is
confirmed by its own Environmental Justice Analysis, which
reported that:
Data from this study indicate that a majority of
respondents, from all groups, feel that their views either have
not been heard, or have been heard, but not acted on. These
findings call into question the effectiveness of the current
public involvement process.
(DEIS Appendix C, p. C-104).
and:
Findings from this study indicate that many respondents
felt that the scoping process did not allow for or welcome input
from the public. (DEIS Appendix C, p. C-104)
This systematic exclusion of the public from meaningful
participation in the NEPA process for the proposed Devils Lake
outlet is further compounded by the abbreviated 60-day comment
period for the DEIS and its appendices imposed by the Corps,
which, after spending five years and $11,000,000 preparing these
complex and confusing three-inch documents (U. S. Army Corps of
Engineers and North Dakota State Water Commission, 2001) while
the lake was rising, now attempts to justify a patently
inadequate public comment period under the transparent guise of
the urgency to make decisions about alternatives and
construction at a time when the lake level is expected to
remain stable or decline (Associated Press, 2001a).
If for no other reason, this pervasive exclusion of the public
from meaningful participation in the EIS process renders the DEIS
inadequate in meeting the Corps statutory responsibilities
under NEPA. Consequently, the only avenue available to the Corps
at this point for achieving compliance with the public
participation and disclosure requirements of NEPA is to withdraw
the DEIS and implement a proper EIS process designed to comply in
good faith with both the spirit and the letter of the statute.
Inappropriate
Tiering of Environmental Impact Analysis
The DEIS states that:
The primary purposes of this Integrated Report, in
accordance with the authorizing legislation, are 1) to implement
tiering as provided in Council on Environmental
Quality (CEQ) Regulation 15.28(b) and 2) to evaluate an outlet
plan (proposed action being evaluated). Tiering procedures allow
for supplemental EIS documentation. (DEIS p. 1-S-1)
However, the Corps and NDSWCs March 1998 Devils
Lake Emergency Outlet Newsletter discussing the 1997
Emergency Supplemental Appropriations Act (Public Law 105-18) and
the 1998 Energy and Water Development Appropriations Act (Public
Law 105-62) under which preparation of the EIS was authorized
makes no mention of tiering of the EIS being
authorized and states only that the project must be in
compliance with the National Environmental Policy Act (U.
S. Army Corps of Engineers and North Dakota State Water
Commission, 1998). Similarly, their March 2001 Devils Lake
Study Newsletter discussing new directions for
the study states only that:
The Corps will use its authority and funding to continue
collecting data and evaluating alternatives to address the
flooding problems at Devils Lake. This will include conducting
the necessary environmental impact evaluations required by NEPA
and the Boundary Waters Treaty of 1909. (U. S. Army Corps
of Engineers and North Dakota State Water Commission, 2001)
Nevertheless, the tiering employed by the Corps in
the DEIS still is not in compliance with Council on Environmental
Quality Regulation 15.28(b). Under CEQ Regulation 15.28 Tiering:
Tiering refers to the coverage of general
matters in broader environmental impact statements (such as
national program or policy statements) with subsequent narrower
statements or environmental analyses (such as regional or
basinwide program statements or ultimately site-specific
statements) incorporating by reference the general discussions
and concentrating solely on the issues specific to the statement
subsequently prepared. Tiering is appropriate when the sequence
of statements is:
From a program, plan or policy environmental impact statement to
a
program, plan, or policy statement or analysis of lesser scope or
to a site-specific statement or analysis.
From an environmental impact statement on a specific action at an
early
stage (such as need and site selection) to a supplement (which is
preferred) or a subsequent statement or analysis at a later stage
(such as environmental mitigation). Tiering in such cases is
appropriate when it helps the lead agency to focus on the issues
which are ripe for decision and exclude from consideration issues
already decided or not yet ripe.
Because the proposed outlet from Devils Lake clearly is not a
part of a program, plan or policy of greater scope but deals with
a project at a specific site, the Corps makes no claim that
tiering of the DEIS is provided under Regulation 15.28(a), but
instead cites section 15.28(b) as its authority.
It is stated in DEIS Appendix C that:
Next Page: 2