Back to Draft Page
Draft Comments by Minnesota Department of Health
May 7, 2002
District Engineer
St. Paul District, Corps of Engineers
Attention: Dave Loss, PM-A
190 Fifth Street East
St. Paul, Minnesota 55101-1638
Dear Mr. Loss:
Thank you for the opportunity to comment on the draft Integrated
Planning Report and Environmental Impact Statement for the Devils
Lake, North Dakota, Outlet Study. The Minnesota Department of
Health (MDH) acknowledges that the recent rise of Devils Lake
water levels has posed, and continues to pose, risk to
development and community services in the area, and has created a
difficult situation for area residents. The efforts to address
these risks need to be effective, efficient, and environmentally
sound. We offer the following comments for your consideration.
Purpose and Need of the Proposed Action. The Corps has identified
the purpose and need of the proposed action as: The purpose
of the proposed action is the reduction of flood damages related
to the rising lake levels in the flood-prone areas around Devils
Lake and to reduce the potential for a natural overflow
event. The original purpose set forth in the February 1999
Corps Scoping Document was confined to reduction of flood damage
and flood protection costs. Congressional interests were
successful in expanding the scope to evaluate possible downstream
impacts of a natural overflow. USGS Fact Sheet FS-089-00
published in June 2000 states that the natural condition for
Devils Lake is either rising or falling, and the lake should not
be expected to remain at any one elevation for a long period of
time. Page 2-2 of the EIS agrees with that conclusion. This is
substantiated by the fact that as recently as the early
1990s Devils Lake interests supported an inlet structure to
increase lake levels. Any flood damage reduction strategies that
rely on attempting to artificially control the lakes levels
will constantly be at odds with the lakes natural condition
and consequently have less potential for success. Further, the
draft EIS demonstrates very clearly that the potential for a
natural overflow is extremely remote. Minnesota has experienced
success with an evacuation and protection model, which
acknowledges natural conditions and also avoids passing the
problem downstream. It has the added benefit of being a
responsible, locally based solution.
Stochastic Model. The stochastic model cited in the EIS showed a
very low probability of a natural overflow event of 9.4%. A large
number of traces were generated as a way of dealing with the
uncertainty regarding future lake levels. The first 15 years of
the model were based on the assumption that the climatic
conditions would be similar to those experienced during 1980-99,
reflecting the generally wetter conditions Devils Lake has been
experiencing since 1980 (EIS p. 3-4). Despite this wet
start assumption, an outlet would only reduce the chance of
an overflow from 9.4 percent to 4.1 percent. Does this reduction
amount to a statistically significant change? The model predicted
a dry future with average peak lake levels of 1448.1
for 35.6% of the time, a moderate 1 future with
average peak lake levels of 1450.2 for 29.9% of the time, and a
moderate 2 future with average peak lake levels of
1454.9 for 25.0% of the time. Thus, more moderate lake levels are
far more likely to occur as evidenced by the modeling results
(EIS Appendix B, p. B-12). Any analysis of a constructed outlet
should examine more closely the downstream impacts resulting from
these more moderate lake levels. This analysis is critical
because of the greater likelihood of their occurrence and the
fact that more moderate lake levels will significantly change the
water quality in Devils Lake from that predicted in the wet
scenario, and consequently impacts to downstream water
users will potentially be more severe.
Cost Benefit Ratio. The draft EIS acknowledges that no outlet
plan showed a positive cost benefit ratio under standard
procedures. An outlet can only be shown to be economically
justified when the model assumes the extremely wet period from
1993-1999 is repeated three times. It is very improbable that
such unique events will be repeated three times in 21 years. MDH
objects to the use of a scenario that relies on repeating the
seven wettest years of recorded historical data until the lake
spills in order to justify the costs of the project.
Low Risk of Natural Overflow. Our position is that there is
little need to reduce the potential for a natural overflow
event since there is already a low probability of
occurrence. On p.1-S-7 of the draft EIS the Corps states that
although there is a low probability of occurrence, the risks
associated with a natural overflow, together with the opportunity
to reduce the damages around Devils Lake with a reduced rate of
rise on the lake, may make the outlet plan an attractive option.
This seems to be a circular route to justify an outlet. The only
alternative demonstrated to be economically sound using standard
procedures was expanded infrastructure protection. In addition, a
constructed outlet has only limited value in preventing the lake
from rising and expanded infrastructure protection would need to
be implemented regardless.
Downstream Water Quality Impacts. Any of the outlet alternatives
would have adverse effects in downstream receiving waters. The
adverse effects would include: degraded water quality; increased
erosion; increased sedimentation; reduced aquatic habitat value;
higher river stages; minimal increased overbank flooding;
extended duration of inundation; impeded river access; loss of
aquatic resources; loss of riparian habitat; effects on
agricultural uses; effects on water treatment facilities; social
effects; cultural resource losses; effects on irrigation; and,
effects on Tribal resources (EIS P. 1-S-8.). As it is apparent
that none of the outlet alternatives can meet the primary goals
of flood damage reduction, lowering lake levels, or even
prevention of rising lake levels, the construction of an outlet
with downstream water quality impacts is a questionable course of
action at best. On page 1-S-2 of the draft EIS the Corps states
that: further coordination is needed to determine if outlet
alternatives are in compliance with various environmental
standards such as the Boundary Waters Treaty of 1909 and the
Clean Water Act. Please explain what the term further
coordination means and why the important issue of
compliance with environmental obligations found in treaty and
statute is not fully analyzed in the EIS. MDH also wonders how
the above statement can be reconciled to the conclusion reached
on p. 1-S-7 that an outlet would result in increases in the
frequency and duration of events that exceed water quality
criteria on the Red River of the North.
Water Supply Impacts. Impacts on drinking water treatment
facilities have been identified as a major adverse effect of a
constructed outlet.
At the current time, Minnesota does not have any municipal
surface water intakes on the Red River of the North. However, the
March 1999 Barr Report: Devils Lake, North Dakota
Downstream Water Users Study, acknowledges that the city of
East Grand Forks has expressed an interest in using the Red River
of the North in the future and has concerns over the future river
water quality (pp.3-5). Because of this interest Barr gathered
necessary data from East Grand Forks but failed to develop cost
estimates for water supply impacts from a constructed outlet. In
a letter dated April 18, 2001, MDH requested that effects on the
City of East Grand Forks water supply be considered because of
the very real possibility that the Red River could become a
source for the citys drinking water. In addition, in
previous correspondence dated March 23, 1998, multiple Minnesota
state agencies requested that the modeling should assess the
impact of a Devils Lake outlet on water treatment systems
assuming that future water supply demands require withdrawals
from the Red River. The additional cost of treatment that would
be required for Minnesota cities to deliver drinkable water for
their communities must be assessed. We consider the lack of this
information to be a serious deficiency of the draft EIS. Further,
Barr concluded that groundwater is not a likely alternate source
water for municipal users because the only usable water is
contained in surficial aquifers, is of poor quality, and has
insufficient yields. We concur with that conclusion and believe
it is irresponsible to exclude a major city in the region from
the consideration of impacts.
An outlet would result in increased water treatment costs. Barr
concludes cost increases will result from increased softening
costs and increased capital and operations costs if treatment or
an alternative water supply is required to restore the treatment
facility finished water quality to without-outlet conditions
(p.1-1). Barr is careful to qualify their conclusions by
acknowledging that changing the location or operating regime for
the pump station would likely result in a change in downstream
river water quality (p.2-4). The lack of an operating plan is
significant at this juncture because it does not allow full and
adequate analysis of downstream water quality impacts and impacts
on water supply. The Barr report took a two-phased approach to
developing mitigation strategies for water treatment facilities.
Phase I estimated operating costs to reduce hardness. Phase II
estimated costs of additional hardness removal and additional
treatment needed to bring the with-outlet water to the
without-outlet finished water quality. This analysis was
inadequate in the following respects. The water quality model
used tracked only conservative substances such as TDS, sulfate,
chloride and hardness. The model was not used to track
non-conservative substances such as nitrogen, phosphorus, total
organic carbon, dissolved oxygen, biochemical oxygen demand, and
pH. However, these constituents are also of interest for water
treatment investigations but were not studied by Barr (p.3-7) The
impacts of these substances on water supply should also be
determined to truly understand how a constructed outlet would
impact water supply. None of the constituents tracked by the
model are currently regulated under the U.S. Primary Drinking
Water Regulations. However, sulfate, TDS, and chloride do have
applicable secondary standards. In addition, sulfate has been
placed on the May 2000 Contaminant Candidate List for potential
regulation. Because of the uncertainties with respect to sulfate
regulation, Barr chose not to estimate treatment costs to reduce
sulfate. We question this approach as not protective of public
health and request that future analyses consider any additional
treatment costs for sulfate removal. The Phase I approach that
assumed only existing treatment processes would be used only
removed some of the TDS and had no significant effect on sulfate
concentrations. As a result, secondary standards will likely be
exceeded for sulfate and TDS. It is distinctly questionable
whether consumers would tolerate these exceedences. A more
realistic approach would follow the methodology used in Phase II
where all constituents were removed to pre-outlet operation
concentrations or alternative water sources were identified.
Consequently, our position is that the cost estimates derived
from Phase II model reflect more accurately the mitigation costs
of an outlet and should be used instead of Phase I results in
future analysis. The additional cost of treatment that would be
required for Minnesota cities to deliver drinkable water for
their communities must be assessed.
Finally, an alternative water supply for Grand Forks was assumed
to consist solely of increased withdrawals from the Red Lake
River. However, no analysis was completed to ascertain if the Red
Lake River, under low flow conditions, would be negatively
impacted or capable of meeting the increased demand. This
analysis should be completed.
Alternative Analysis. The alternative analysis was not complete.
The EIS states that all of the impacts and associated mitigation
needs have not been quantified, but the Corps considers the
information adequate to address the decision to be made at this
time, which is identification of alternative(s) for
implementation (p. 1-S-12). However, the Congressional
authorization specifically requires an outlet to be technically
sound, economically justified, environmentally acceptable, and in
compliance with NEPA. In addition, the economic justification
must be fully described, including the analysis of the benefits
and costs, in the project plan documents. Increased water
treatment costs are potentially very significant for downstream
users and should be included in the cost analysis.
Source Water Protection. Source water protection is an accepted
principle of drinking water protection. The construction of an
outlet would adversely affect the ability to use the Red River of
the North as a drinking water source and is not beneficial to
downstream interests. This source is of regional and statewide
significance and the extremely limited benefits of a constructed
outlet do not outweigh the risks associated with it. The
strategies of expanded infrastructure and upper basin storage
offer the most effective, efficient, and environmentally sound
alternatives.
Thank you for the opportunity to provide comments on the
Environmental Impact Statement for the Devils Lake Outlet Study.
As you can see, MDH has some serious concerns regarding the
conclusions of the study, concerns which are shared by several
other Minnesota state agencies. We encourage you to address these
concerns before making a final decision on any action to be taken
by the Corps. If you have any questions about the issues raised
in this letter, please contact Beth Kluthe of our Bemidji Office
at 218-755-4173.
Sincerely,
Patricia A. Bloomgren, Director
Environmental Health Division
P.O. Box 64975
St. Paul, MN 55164-0975
cc: Ron Harnack, Minnesota Board of Water and Soil Resources
Kent Lokkesmoe, Minnesota Department of Natural Resources
Rod Massey, Minnesota Pollution Control Agency
Senator Mark Dayton
Senator Paul Wellstone
Representative Gil Gutknecht
Representative Mark R. Kennedy
Representative Jim Ramstad
Representative Betty McCollum
Representative Martin Olav Sabo
Representative William Luther
Representative Collin Peterson
Representative James Oberstar
Senator Byron Dorgan
Senator Kent Conrad
Representative Earl Pomeroy
Susan A. Thompson, Canadian Consul General, Minneapolis
Gerald Galloway, International Joint Commission, Washington, D.C.